Camp Li-Wa’s new lodge will be a multi-use building with space for an upgraded kitchen, dining area, and ample meeting space.
The lodge has been under construction for a few years now and is approaching completion. Finishing this project is paramount to the growth of Camp Li-Wa programs moving forward. In the last five years, we have seen an overwhelming increase in both our summer and winter programming – reaffirming the immediate need for our new lodge to be “on-line”.
In 2023 we:
-
Finalized interior kitchen framing
-
Built the fireplace case
-
Finalized the electrical rough in
-
Hung Drywall
-
Finalized the heating system
-
Built the loading dock area
-
Built a handicap ramp
In 2024 we plan on:
-
The installation of the kitchen’s air handling
-
The kitchen drop ceiling
-
Kitchen tile and stainless steel wall panels
-
Interior cultured stone
-
Mechanical installation for the walkin fridge and freezer
-
The final electrical trim out
-
Final insulation